MIRACK CONSTRUCTION INC
TEMPE, ARIZONA 852815761
Top Industries (NAICS)
| NAICS Code | Obligations | Awards |
|---|---|---|
| 236220 | $2.18M | 9 |
| 237990 | $1.06M | 8 |
| 238990 | $92K | 2 |
Contract Awards
13 awards found
CONTRACT FOR FY22 MOJAVE INLET REPAIRS PHASE 2 AT HESPERIA, CA. REFERENCE NO. R00007. SD004 REMOB, SD009 ENVIRONMENTAL REQUIREMENTS. CONTRACT PRICE IS INCREASED BY $371,505.51. COMPLETION DATE SHALL BE EXTENDED BY 30 CALENDAR DAYS.
CONTRACT FOR CORONA DIKES REPAIR AT CORONA, CA. REFERENCE NO. R00005 WN006 SEWER DIKE PUNCH LIST ITEMS. TOTAL CONTRACT PRICE IS INCREASED BY $22,725.37. CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 7 CALENDAR DAYS BY REASON OF THIS MODIFICATION.
CONTRACT FOR CORONA DIKES REPAIR AT CORONA, CA. REFERENCE NO. R00004 WN005 STD MOWING AND VEGETATION REMOVAL. TOTAL CONTRACT PRICE IS INCREASED BY $207,341.92. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 42 CALENDAR DAYS BY REASON OF THIS MOD.
CONTRACT FOR CORONA DIKES REPAIR AT CORONA, CA. REFERENCE NO. R00001 WN001 REMOVE TEMP IRRIGATION LINES NHD AND STD. TOTAL CONTRACT PRICE IS INCREASED BY $129,534.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
CORONA DIKE REPAIRS & HYDROSEEDING
CONTRACT FOR MOJAVE INLET REPAIRS AT HESPERIA, CA. REFERENCE NO. R00004, SD006 K-RAIL AND SIGNAGE. TOTAL CONTRACT PRICE DECREASED BY $(27,021.98). THE COMPLETION DATE SHALL BE EXTENDED BY 173 CALENDAR DAYS, TO 09/15/2023.
CONTRACT FOR FY22 MOJAVE INLET REPAIRS PHASE 2 AT HESPERIA, CA. REFERENCE NO. R00003, SD005 MAKE SITE SAFE. TOTAL CONTRACT PRICE IS INCREASED BY $36,205.78. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
CONTRACT FOR FY22 MOJAVE INLET REPAIRS PH2, HESPERIA, CA. REF.NO.R00002 SD002 REPAIR ROADS, RAMP & CLEAN DEBRIS. TOTAL CONTRACT PRICE IS INCREASED BY $19,004.11. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
CONTRACT FOR FY22 MOJAVE INLET REPAIRS PH2 HESPERIA, CA. REF.NO.R0001 SD001 ACCELERATION AND REBUILD ACCESS RAMP. TOTAL CONTRACT PRICE IS INCREASED BY $60,975.05. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
MOJAVE DAM WINGWALL INLET REPAIRS PH II, HESPERIA, CA
CONTRACT FOR FDA IRVINE FACILITY WL REPLACEMENT. REFERENCE NO. R00001 WN002 COMM VAULT RELOCATION. TOTAL CONTRACT PRICE IS INCREASED BY $43,827.00. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 60 CALENDAR DAYS.
CONTRACT FOR US FDA PARKING LOT MITIGATION AT IRVINE, CA. REFERENCE NO. R00004 WN005 DEFICIENT EXISTING ELECTRICAL WORK. THE CONTRACT PRICE IS INCREASED BY $49,704.55. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
CONTRACT FOR US FDA PARKING LOT MITIGATION AT IRVINE, CA. REFERENCE NO. R00003 WN004 RFI-0022 TREATED BASE AND MOISTURE. TOTAL CONTRACT PRICE IS INCREASED $42,283.67. CONTRACT SHALL BE EXTENDED 15 CALENDAR DAYS.
Business Details
- UEI
- DG4ERBLG1HR6
- CAGE Code
- 5WYM8
- Address
- 1801 S JENTILLY LN STE D-18
TEMPE, AZ 852815761 - Congressional District
- AZ-04
- Phone
- 5206311448
Parent Company
MIRACK CONSTRUCTION INC
Data Source
This profile is based on federal contract award data from USAspending.gov.