DEOBLIGATE MONEY AS THIS IS A PART OF A CBCA SETTLEMENT AND WILL BE ISSUED ON ANOTHER MODIFICATION.
TO PROVIDE ADDITIONAL FUNDING BASED ON POST AUDIT RESULTS.
TO PROVIDE ADDITIONAL FUNDING BASED ON POST AUDIT RESULTS. TO CHANGE THE LINE OF ACCOUNTING ON P00089.
TO PROVIDE ADDITIONAL FUNDING BASED ON POST AUDIT RESULTS
THIS MODIFICATION PROVIDES REIMBURSEMENT OF THE EXPENSE FOR THE FINAL PAYMENT OF ELECTRIC SERVICE FROM SUBSTANTIAL COMPLETION 07/03/2024 THROUGH 08/02/2024.
THIS MODIFICATION PROVIDES ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED FOR FAN COIL RELIEF AS OUTLINED IN RESPONSE TO RFI 60, AND FOR THE EXHAUST FAN MODIFICATIONS OUTLINED IN RESPONSE TO RFI 595.
1) THIS MODIFICATION PROVIDES FOR THE INSTALLATION GFCI PROTECTED RECEPTACLES IN ACCORDANCE WITH NFPA 70.210.8.AND DELETES THE REQUIREMENT FOR A CHAIN LINK FENCE.
THIS MODIFICATION PROVIDES ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED FOR THE BUILDING A SMOKE DAMPERS, THE ADDITION OF 3 SQUARE CATCH BASINS, ADJUSTMENTS THE WATER HEATER AT BUILDING E, CREDITS TO THE GOVERNMENT AND OTHER MISCELLANEOUS ITEMS FOR THE
THIS MODIFICATION PROVIDES FOR THE REVSIONS IN CONSTRUCTION REQUIRED FOR THE PROPER INSTALLATION OF THE COILING DOOR IN BUILDING F FOR THE REDEVELOPMENT OF THE GULFPORT JOB CORPS CENTER.
THIS MODIFICATION PROVIDES FOR AN INCREASE IN HOURLY RATES FROM $16.20 PER HOUR TO $17.20 PER HOUR.
THIS MODIFICATION PROVIDES FOR FINAL SETTLEMENT OF ALL COSTS ASSOCIATED WITH THE NOTICE TO PROCEED WITH FOR THE ADDITIONAL WORK IN RESPONSE TO REQUEST FOR INFORMATION NO. 504, BUILDING A DRYWALL COLUMN COVERS.
THIS MODIFICATION PROVIDES FOR THE ADDITIONAL COST INCURRED FOR THE INSTALLATION OF 6" ROOF DRAIN PIPES IN LIEU OF THE 4" DRAIN PIPES SPECIFIED BY CONTRACT AT BUILDING F.
THIS MODIFICATION PROVIDES A CREDIT TO THE GOVERNMENT AS A RESULT OF THE REVISIONS IN CONSTRUCTION WHICH DELETES THE REQUIREMENT FOR MANHOLE 5 AT BUILDING A.
THIS MODIFICATION PROVIDES COMPLETE SETTLEMENT OF ALL COSTS INCURRED BY ROY ANDERSON CORPORATION (RAC) DUE TO THE STRUCTURAL STEELS ISSUES ENCOUNTERED AT BUILDING A DURING THE DEVELOPMENT OF THE GULFPORT JOB CORPS CENTER.
THIS MODIFICATION PROVIDES ALL LABOR, MATERIAL AND EQUIPMENT FOR THE REVISIONS TO THE EXISTING WALLS AT BUILDING A, AS OUTLINED IN THE GOVERNMENT'S RESPONSE TO RFI 404, 401 AND 398.
THIS REVISIONS PROVIDES ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED FOR CHANGES TO THE GRADING AND THE ELIMINATION OF CHAIN WALLS AT THE EAST SIDE OF BUILDING F FOR THE REDEVELOPMENT OF THE GULFPORT JOB CORPS CENTER.
THIS REVISIONS PROVIDES ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED FOR THE IN-FIELD FRAMING ADJUSTMENT AS DESCRIBED UNDER ASI NO.13 FOR BUILDING A AT THE GULFPORT JOB CORPS CENTER.
THIS REVISIONS IN CONSTRUCTION PROVIDES ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED FOR THE ADDITION AND INSTALLATION OF A 3"PIPE WITH HUB DRAIN IN RESPONSE TO PCO 032, TITLED COOLING TOWER DRAIN, FOR THE REDEVELOPMENT OF THE GULFPORT JOB CORPS C
THIS REVISIONS IN CONSTRUCTION PROVIDES ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED TO COMPLETE THE MASONRY REPAIRS FOR THE EXISTING SOUTH WALLS AT BUILDING A.
THIS REVISIONN PROVIDES FOR ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED TO ALLOW FOR THE IMPLEMENTATION OF THE SERVICES OUTLINED IN THE JUNE 3, 2023, NOTICE TO PROCEED, WITH THE GROUT WORK AT BUILDING A.
THIS REVISION IN CONSTRUCTION PROVIDES ALL LABOR, MATERIAL AND EQUIPMENT TO ALLOW FOR THE IMPLEMENTATION OF THE SERVICES OUTLINED IN REQUEST FOR PROPOSAL 002 DATED MAY 12, 2023 AND ITS ASSOCIATED SCOPE OF WORK DATED MAY 11, 2023 TO INCLUDE 3/4"
THIS ITEM PROVIDES FINAL SETTLEMENT OF ALL COSTS ASSOCIATED WITH THE DELAYS ASSOCIATED WITH UNFORESEEN UNDERGROUND OBSTRUCTIONS AND UNFORESEEN ASBESTOS ENCOUNTERED IN BUILDING A, PCO 21R3.
THIS ITEM PROVIDES FOR ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED TO REMOVE THE EXISTING MASONRY, CLEAN AND PAINT THE EXISTING STEEL, AND INSTALL THE NEW C-CHANNELS AS OUTLINED IN THE SCOPE OF WORK DATED MARCH 7, 2023.
THIS ITEM PROVIDES REIMBURSEMENT OF RAC TO PROVIDE ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED TO REMOVE ALL UNSUITABLE SOIL INTERFERING WITH THE INSTALLATION OF FOUNDATION F23A TO BE REPLACED WITH FLOWABLE FILL.
THIS ITEM PROVIDES REIMBURSEMENT OF ALL COSTS ASSOCIATED WITH THE IMPLEMENTATION OF MINIMUM WAGE INCREASE EFFECTIVE JANUARY 1, 2023.
PURSUANT TO THE GOVERNMENT RESPONSE TO RFI 186, THIS MODIFICATION WILL PROVIDE ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED FOR THE HOOK BARS ADDED TO THE FOUNDATIONS OF BUILDING F, COLUMN LINE F4. THIS REVISION IN CONSTRUCTION INCLUDES THE COSTS FOR
MODIFICATION NO. P00005 IS DELETED IN ITS ENTIRETY, WHICH RESULTS IN A CREDIT TO THE GOVERNMENT FOR ALL LABOR, MATERIALS AND EQUIPMENT AS OUTLINED IN THE EXECUTED MODIFICATION.
RAC SHALL PROVIDE ALL LABOR, MATERIALS AND EQUIPMENT REQUIRED TO PROVIDE THE TEMPORARY OFFICES REQUIRED IN ACCORDANCE WITH SECTION SECTION 1.3.D., OF THE CONTRACT SPECIFICATION.
THIS MODIFICATION PROVIDES FOR ALL LABOR, MATERIALS AND EQUIPMENT REQUIRED FOR THE CHANGES IN THE HARDWARE SCHEDULE, AND FOR THE DELETION OF PIERS AT BUILDING A.
TO PROVIDE ADDITIONAL ATS TRAINING
THIS MODIFICATION PROVIDES FOR ALL LABOR, MATERIALS AND EQUIPMENT REQUIRED TO MAKE PILE AND GRADE BEAM CHANGES AT BUILDING F DUE TO THE UNFORESEEN FORCE SEWER MAIN.
THIS MODIFICATION PROVIDES FOR THE ADDITIONAL EXCAVATION TO UNCOVER AND REPAIR AN EXISTING FORCE SEWER MAIN AT BUILDING F AND PROVIDES A CREDIT TO THE GOVERNMENT FOR WORK NO LONGER REQUIRED.
THIS MODIFICATION PROVIDES FOR ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED TO IMPLEMENT THE REVISIONS IN CONSTRUCTION REQUIRED AS A RESULT OF THE CITY OF GULFPORT, EGH AND THE ESC REVISIONS IN DESIGN AS OUTLINED EGH'S SYNOPSIS OF CHANGE DATED JUL
THE CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED FOR THE REMOVAL OF ADDITIONAL ASBESTOS CONTAINING MATERIALS DISCOVERED IN THE BATHROOMS AT BUILDING A.
THIS MODIFICATION RESOLVES THE RAC'S MAY 4, 2002, REQUEST FOR ADDITIONAL COST ASSOCIATED WITH THE IMPLEMENTATION OF E.O. 14024, AND DOWNTOWN ASSOCIATED WITH EXPLORATORY BORINGS FOR THE CENTER REDEVELOPMENT PROJECT AT THE GULFPORT JOB CORPS CENTE
UNDER CHANGE ORDER NO. 001 REQUIRES ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED TO REMOVE AN ADDITIONAL 1,000 CUBIC YARDS OF DIRT/DEBRIS AT BUILDING F.
THIS MODIFICATION PROVIDES ALL LABOR MATERIAL AND EQUIPMENT REQUIRED TO PERFORM EXPLORATORY BORING AT BUILDING F, AND TO MODIFY THE EXISTING WALL OF THE GYMNASIUM.
THIS REVISION IN CONSTRUCTION REQUIRES ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED TO REMOVE UP TO 1,000 CUBIC YARDS OF DIRT/DEBRIS AT BUILDING F.
THIS MODIFICATION REQUIRES ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED TO REWORK THE SOUTH BANK OF BRICKYARD BAYOU.
THIS MODIFICATION REQUIRES ALL LABOR, MATERIAL AND EQUIPMENT REQUIRED FOR THE RELOCATION OF AN EXISTING WATER MAIN AT BUILDING F.
THIS MODIFICATION SETTLES RAC'S ADDITIONAL COSTS FOR MANAGEMENT, SUPERVISION, ADMINISTRATION AND ESCALATION COSTS ASSOCIATED DUE TO PROTEST, CE#001.
Business Details
- UEI
- WMX2JXNH41J8
- CAGE Code
- 0C6F6
- Address
- 11400 REICHOLD RD
GULFPORT, MS 395036008 - Congressional District
- MS-04
- Phone
- 2288964000
Data Source
This profile is based on federal contract award data from USAspending.gov.
View on USAspending.gov