28 awards found
DEAN S. RECREATION SITE
TALKINGTON DAM REPAIR ENTAILS RESTORING FULL FUNCTIONALITY TO WATER IMPOUNDMENT BY REPLACING FAILED OUTLET WORKS. THE IMPOUNDMENT IS CRITICAL FOR PROVIDING A WATER SOURCE FOR WILDLAND FIREFIGHTING EFFORTS AND STOCK WATER SUPPLY IN WESTERN NORTH DAKOT
SIOUX BLOWDOWN DISASTER RELIEF
MOD 003 - ADD QUANTITIES FOR THE FINAL SURVEY OF WASTE REMOVAL - RILEY PASS FY25 2025 BLUFF B RECLAMATION PROJECT
MOD 002 - DEOBLIGATE AND CLOSE OUT - THE WORK SHALL BE PERFORMED ON BLUFF B, WHICH INVOLVES EXCAVATING HISTORIC MINE WASTES AT VARIOUS LOCATIONS ON BLUFF B, PLACING AND COMPACTING THE MINE WASTES IN CONSOLIDATION AREAS.
GAOA - FOREST-WIDE TOILET REPLACEMENT: INSTALLATION OF CONCRETE TOILETS ACROSS THE BEAVERHEAD-DEERLODGE NF RANGER DISTRICTS IN SW MONTANA
RILEY PASS FY25 2025 BLUFF B RECLAMATION PROJECT
DEAN S. RECREATION SITE
TALKINGTON DAM DRAINAGE STRUCTURE REPLACEMENT DPG
RILEY PASS FY25 2025 BLUFF B RECLAMATION PROJECT
TALKINGTON DAM DRAINAGE STRUCTURE REPLACEMENT DPG
ASHLAND WAREHOUSE WATERLINE REPAIR/REPLACEMENT CGNF
GAOA SIOUX REC SITE TOILET REPLACEMENT PROJECT CGNF
GAOA SOUTH DAKOTA BRIDGE REPLACEMENTS
GAOA MAAH DAAH HEY TRAIL REROUTE AND TRAILHEAD PARKING LOT DAKOTA PRAIRIE GRASSLANDS
THE WORK SHALL BE PERFORMED ON BLUFF B, WHICH INVOLVES EXCAVATING HISTORIC MINE WASTES AT VARIOUS LOCATIONS ON BLUFF B, PLACING AND COMPACTING THE MINE WASTES IN CONSOLIDATION AREAS.
HORSE CREEK CULVERT REPLACEMENT PHASE II, ROAD REALIGNMENT, ABANDONED ROADWAY OBLITERATION, STRUCTURE REMOVAL
GAOA SIOUX REC SITE TOILET REPLACEMENT PROJECT CGNF
THE WORK SHALL BE PERFORMED ON BLUFF B, WHICH INVOLVES EXCAVATING HISTORIC MINE WASTES AT VARIOUS LOCATIONS ON BLUFF B, PLACING AND COMPACTING THE MINE WASTES IN CONSOLIDATION AREAS.
THIS MODIFICATION INCORPORATES THE FINAL ADJUSTMENT TO THE CONTRACT'S PERIOD OF PERFORMANCE ALONG WITH THE ASSOCIATED EQUITABLE ADJUSTMENT. A REDUCTION OF $513.50 PER DAY FOR THIS EXTENSION IS THE COMPLETE, EQUITABLE, AND FINAL ADJUSTMENT FOR T
EXCAVATING HISTORIC MINE WASTES AT VARIOUS LOCATIONS ON BLUFF B, PLACING AND COMPACTING THE MINE WASTES FOR LANDFORM CONSTRUCTION, AND PROVIDING AND PLACING COVER SOIL.
CG EMERGENCY FLOOD RESPONSE- WEST FORK ROCK CREEK TEMPORARY ACCESS WPAP# 631427
EXCAVATING HISTORIC MINE WASTES AT VARIOUS LOCATIONS ON BLUFF B, PLACING AND COMPACTING THE MINE WASTES FOR LANDFORM CONSTRUCTION, AND PROVIDING AND PLACING COVER SOIL.
EXCAVATING HISTORIC MINE WASTES AT VARIOUS LOCATIONS ON BLUFF B, PLACING AND COMPACTING THE MINE WASTES FOR LANDFORM CONSTRUCTION, AND PROVIDING AND PLACING COVER SOIL.
RILEY PASS,BLUFF A RESPONSE ACTION, MODIFICATION P00004 DE-OBLIGATE AND CLOSE
THIS MODIFICATION INCORPORATES A TIME EXTENSION WITH CONSIDERATION IN RESPONSE TO THE CONTRACTOR'S REQUEST DATED SEPTEMBER 15, 2022 AND IN RESPONSE TO THE GOVERNMENT NEEDING TO ENTER A SECOND WINTER SHUTDOWN/RESUMPTION OF WORK PROCESS.
CG EMERGENCY FLOOD RESPONSE- WEST FORK ROCK CREEK TEMPORARY ACCESS WPAP# 631427
THIS MODIFICATION INCORPORATES A REQUEST FOR EQUITABLE ADJUSTMENT IN RESPONSE TO THE CONTRACTOR'S REQUEST SUBMITTED ON JUNE 6, 2022.
Business Details
- UEI
- CDWJT9E6C3X9
- CAGE Code
- 5GRU6
- Address
- 10544 TUFTE RD
LUDLOW, SD 577555014 - Congressional District
- SD-00
- Phone
- 7015231289
Parent Company
YOUNG GUN CONSTRUCTION LLC
Data Source
This profile is based on federal contract award data from USAspending.gov.
View on USAspending.gov